Rough Schedule:
10/3: all characters rigged and textures ready
10/10: all characters painted and textured, and setting completed
10/17: X
10/24: short animated up to the second petals descent
10/31: lighting finished and set completed (including textured)
11/7: short animated up to falling into the fountain
11/14: short fully animated and camera's in place
11/21-12/6: rendering
Following this schedule we, team rags, plan to have our portfolio short ready and finished. The music will be composed parallel to our schedule by members of the music department. Further details on their evolvement will be posted on the blog as they transgress.